Mangere Refugee Centre
Client: Downer Group
Culham Engineering detailed, fabricated and erected approximately 70 Ton of Structural Steel for the new Refugee Centre in Mangere.
All members were phased according to the contractors build program to ensure that there was no delay to critical path items such as concrete floor pours. The project was a traditional ‘stick build’ structure and all lifts were performed using Culham Engineering mobile cranes. The project was completed on time and within budget.